Bridges Construction

The Bridge Over Artificial River ( Chu Dong Tu Bridge)

THE PROJECT

Project name: Design and Construction of Chu Dong Tu Bridge and Approach Road under under the Project of Hanoi-Hung Yen Interprovincial Transportation Route.

Bridge type: Arch bridge, 5-span continuously reinforced concrete beam and slab structure.

Location: Van Giang district, Hung Yen Province, Vietnam.  

Total Bridge Length: 105.0m x 2 bridges

Bridge Longest Span: 21m

Deck Width: 22.25m X 2 bridges

 

Client:  VIET HUNG URBAN INVESTMENT AND DEVELOPMENT JSC ( VIHAJICO )

EPC Main - Contractor: Joint Venture Contractors: UTRACON OVERSEAS PTE. LTD (SINGAPORE) & UTRACON VIETNAM CO., LTD

The Engineer : Joint Venture Hung Phu - Vihaconsult

Construction Period: 11/ 2016 – 05/ 2019

 

CONSTRUCTION METHOD

Pile Foundation: PHC Pile.

Soft Ground Treatment: Vertical Drain & Surcharge method.

Superstructure: Full staging method.

 

UTRACON'S INVOLVEMENT

Our scope of works involved as General Contractor: Design and Construction of the whole package under EPC (Engineering, Procurement & Construction) Contract package.

 
 

 