The Bridge Over Artificial River ( Chu Dong Tu Bridge)
THE PROJECT
Project name: Design and Construction of Chu Dong Tu Bridge and Approach Road under under the Project of Hanoi-Hung Yen Interprovincial Transportation Route.
Bridge type: Arch bridge, 5-span continuously reinforced concrete beam and slab structure.
Location: Van Giang district, Hung Yen Province, Vietnam.
Total Bridge Length: 105.0m x 2 bridges
Bridge Longest Span: 21m
Deck Width: 22.25m X 2 bridges
Client: VIET HUNG URBAN INVESTMENT AND DEVELOPMENT JSC ( VIHAJICO )
EPC Main - Contractor: Joint Venture Contractors: UTRACON OVERSEAS PTE. LTD (SINGAPORE) & UTRACON VIETNAM CO., LTD
The Engineer : Joint Venture Hung Phu - Vihaconsult
Construction Period: 11/ 2016 – 05/ 2019
CONSTRUCTION METHOD
Pile Foundation: PHC Pile.
Soft Ground Treatment: Vertical Drain & Surcharge method.
Superstructure: Full staging method.
UTRACON'S INVOLVEMENT
Our scope of works involved as General Contractor: Design and Construction of the whole package under EPC (Engineering, Procurement & Construction) Contract package.