Post-tensioned Buildings

MG 51 New Factory

 THE PROJECT

 

The project is built on a total area of 5 hectares with strict requirements on the progress and quality of the investor and main contractor Obayashi. Construction of over 60 tons of stand in 25 days.

UTRACON Vietnam Co., Ltd. awarded the package of design and construction for Post-tensioning beam-slab. With our experience, provision sufficient resource in manpower and equipment, we meet safety,  technical requirements, and quality of the Project. 

Location: Lo CN5.20, Dinh Vu IP, Dong Hai 2, Hai An District, Hai Phong City

   
Client: SHIN-ETSU MAGNETIC MATERIALS VIETNAM
 

Main contractor: OBAYASHI Viet Nam Corporation

 

Period:  9/2018 – 12/2018

 
 
UTRACON’S INVOLVEMENT
 
Our scope of works involved design, supply and installation of Post-tensioning works in beam and slab.