THE PROJECT

DAIKIN VIETNAM factory was built at Lot Q1, Thang Long Industrial Park II, Phung Chi Kien Ward, My Hao Town, Hung Yen Province, Vietnam. Layout area is 219,074 m2, total floor area 16,000m2.

UTRACON Vietnam Co., Ltd has won the package of design and construction of Post-tensioning works for the DAIKIN VIETNAM EXTENSION PROJECT. 

With our experience in the PT field and advanced machinery and equipment, We have met successfully the technical requirements, progress and quality of the project. Standards of working safety and environment protection are followed strictly.

 

Client: Daikin Air Conditioning (Vietnam) JSC - Hung Yen Branch

Main contractorObayashi Vietnam

Period 06/2022 – 08/2022

 
UTRACON'S INVOLVEMENT

Our scope of works involved in design, supply and installation of Post-tensioning works in beam and slab.

 

  

  
 
  
 
 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 